Cadenasso Drive Pavement Reconstruction Project
General Work Description: The City of Fairfield proposes a pavement preservation project on Cadenasso Drive from approximately 160’ West of Magellan Road to Beck Ave. The work will include using hot mix asphalt, ADA Ramp Upgrades, adjusting utilities to grade, and adding striping/pavement markings. Project approval also includes 2.5-inch mill and overlay with fabric for Auto Mall parkway from Laurel Creek Bridge (approximately 300’ East of Hamilton Drive) to 160’ West of Magellan Road. All work will be completed within local right-of-way.
Status
Bidding Closed
Bid Date | 1/16/24 2:00pm |
Company & Contacts
City of Fairfield, CA
Phil Layoso
707-428-7505
Location
Fairfield, CA
The Engineer's Estimate is $2,650,000